11th Street Sidewalk
11th Street Sidewalk
11th Street is closed to through traffic from Baker Street to Ames Street beginning Monday, February 12. A Kansas Department of Transportation contractor, Killough Construction, is constructing a sidewalk along the west side of 11th from Ames to High Street.
Road closed between Baker and Ames Streets
Project Timeline
A rough timeline of the entire project is as follows:
- 11th street sidewalk, including the drainage infrastructure work between Baker and Ames, will continue through late March. The road will remain closed to through traffic during that time.
- The High Street segment from 4th to 2nd from approximately late March into early April.
- 2nd Street sidewalk from Fremont to Highway 56 in April.
- Quayle Street sidewalk from 6th to the Junior High in late April.
All of this timing is approximate and weather dependent.